Tuesday, September 14, 2010
Getting the test model ready.
Valley Christian's International Space Station team is getting ready to test their first experimental cube lab. The testing will occur from October 4th through the end of November. They experimental module will go through numerous and rigorous testing. The testing will consist of an electromagnetic Interference test that will take place at Huntsville, Alabama at Marshall Flight Space Center. There will also be out gassing tests at the University of Kentucky. The acoustic and vibration testing have been cancelled due to the protection provided by the ESD material on the Japanese booster. Also the depressurization testing will be done at the University of Kentucky, the module will be depressurized from 14.8 PSI down to 4 PSI at an interval of 30 seconds. All this must be done to insure the sucess of the project.
Friday, July 23, 2010
Project Overview
The project steps will be recorded in a documentary video that will be filmed and produced by VCHS students.
IV. Student Time Commitment
In order to meet this aggressive schedule, VCS will select the ISS Project Student Team members by the end of April 2010 and start working on the project with the student during the summer of 2010; and, it will continue through the 1st semester of the 2010-2011 school year. During the first quarter of 2011, data from the CUBE-LAB aboard the ISS will be downloaded to the students and it will aggregated, analyzed, and a report will be written by the students on their findings.
The time commitment for a student on ISS Project team is in three parts, as follows:
Part-I: Summer 2010 (45 Hours):
July 12-16 1:30-4:30PM
July 19-23 1:30-4:30PM
July 26-30 1:30-4:30PM
Part-II: August – October 2010-2011 (55 hours)
Weekly, after school Tuesdays and Thursday (2 hours each day)*
Weekly, Saturday AM (2 hours)*
*Note: Some students may not be able to meet all three days (Tuesdays, Thursdays and Saturdays) each week during the school year. Students needing to be excused from certain meeting dates will need to work with the ISS project team to stay current with their work commitments on this project.
Part-II February – March 2011 (35 hours)
The project experiment aboard the ISS will be monitored for 30 days during Q1 of 2011. Students from the project team will aggregate data daily (1hr x 30days) and report (5hrs) on this project by the end of March.
Students are also expected to work this project aside from the above schedule times if work is not completed during the project team meeting times.
The ISS Project goal is for students to be able to balance their school commitments with the success of the ISS Project. All students that participate in this program have much to gain if the project is a success.
V. Project Timeline
Click here for a larger image of the project schedule
Wednesday, July 14, 2010
Valley Christian Cubelab Experiment Signing
The project begins immediately with the selection of students from Valley Christian Schools new K-12 Applied Mathematics, Science and Engineering Institute (AMSE). The CUBE-LAB experiment is expected to fly to the U.S. National Laboratory on the International Space Station during the 1st Quarter of 2011. Students will aggregate and analyze their data each day upon transmission to earth. Valley Christian Schools’ AMSE Institute students will produce a video documentary to inspire students from other high schools to launch similar projects. Valley Christian Schools made the agreement with NanoRacks, LLC to secure a space for the microgravity experiment aboard the U.S. National Laboratory on the International Space Station in collaboration with the Quest Institute for Christian Education.